IT operations

UPS Manager

UPS units monitored over SNMP or NUT, with a graceful shutdown of the servers during a power outage.

Version
1.2.0
Stage
Stable
Screenshots
3
Replaces
Each UPS vendor’s own software (Eaton IPM, EcoStruxure)
The status of the 6 UPS units. Each card shows the battery, load, runtime, and temperature, plus the power-flow diagram. The UPS in Ploiești went on battery at 09:18 and stands out immediately: the card and the diagram change color, and the outage reaches SOC as a critical alert.
The status of the 6 UPS units. Each card shows the battery, load, runtime, and temperature, plus the power-flow diagram. The UPS in Ploiești went on battery at 09:18 and stands out immediately: the card and the diagram change color, and the outage reaches SOC as a critical alert.

Screenshots from the application

What it looks like at work

The real Monolit interface, with data from a fictional company on a typical day. The interface in the screenshots is in Romanian. Click a screenshot to see it at full size.

Voltages and trends for each UPS. The expanded panel shows the voltages, the power, and the battery, load, and runtime chart. UPITPL0001 shows the discharge over the last 23 minutes, compared with the Bucharest UPS units, which are on utility power.
Screenshot 2 of 3

Voltages and trends for each UPS

The expanded panel shows the voltages, the power, and the battery, load, and runtime chart. UPITPL0001 shows the discharge over the last 23 minutes, compared with the Bucharest UPS units, which are on utility power.

Graceful shutdown by group. The “Bucharest server room” group (Camera servere București) links two UPS units to 9 servers and sets the shutdown order by runtime threshold: first the applications, then the database, the domain controller, the Proxmox hosts, and the storage.
Screenshot 3 of 3

Graceful shutdown by group

The “Bucharest server room” group (Camera servere București) links two UPS units to 9 servers and sets the shutdown order by runtime threshold: first the applications, then the database, the domain controller, the Proxmox hosts, and the storage.

1Level 1

For leadership

What problem it solves, how the team works with the module, and what can be measured.

What problem it solves

A power outage that lasts longer than the UPS runtime shuts servers down abruptly. The typical result: corrupted databases, lost files, and hours of manual restarts. Often no one finds out in time that a UPS has switched to battery, especially at a site without IT staff.

UPS Manager monitors all of the company’s UPS units from a single screen and shuts servers down in the set order before the batteries run out.

What it does in practice

  • Reads the status of each UPS over the network: battery level, load, remaining runtime, temperature, and input and output voltages.
  • Shows a power-flow diagram for each UPS. When utility power is lost, the diagram and the card change color immediately.
  • Keeps a history of the measurements and charts the recent trend of battery, load, and remaining runtime.
  • Groups UPS units with the servers they power. For each server, you set the remaining runtime at which it shuts down.
  • When power is lost, automatically shuts servers down one by one as their thresholds are reached, each only once, even if Monolit restarts during the outage. When power returns, it can start back up via Wake-on-LAN only the servers it shut down; a server deliberately shut down by a person stays off.
  • Sends email and SMS alerts, with the levels (info, warning, critical) chosen separately for each channel. A shutdown that could not be completed or confirmed triggers a critical alert.
  • Keeps a log of every shutdown and every Wake-on-LAN startup, automatic or manual, exportable to CSV.
  • Automatically discovers the UPS units in a subnet.
  • UPS units and the servers they power appear on the infrastructure map built by the Monitoring module. Outages also reach SOC, as operational issues, without raising the threat level.
  • Configuration, server shutdown, and Wake-on-LAN are for administrators and the IT manager only; the rest of the IT team sees the status.

Workflows

1. A power outage at one site

  1. The UPS switches to battery. Monolit sends an email warning, and in SOC the outage appears as a critical alert. SMS can be reserved for critical events, for example the start of a server shutdown.
  2. The UPS card turns yellow; the group shows the remaining runtime and the threshold at which shutdown begins.
  3. If runtime drops below the threshold, the servers in the group receive the shutdown command in the configured order, each only once.
  4. When power returns, the servers marked for automatic startup that Monolit shut down during this outage start via Wake-on-LAN, after the set delay. A server shut down manually stays off. If power returns only briefly, startup waits until power is back for good.
  5. Everything stays in the log, with the time, the result, and the duration of each operation.

2. Scheduled electrical maintenance

  1. The IT manager or an administrator opens the affected group and clicks “Shut down all”.
  2. The servers shut down in staggered order, following the timeline.
  3. After the work, the physical servers are started via Wake-on-LAN from the same page.

3. Periodic check

  1. Before maintenance, the IT manager runs “Test connection” on each server.
  2. A failed test (for example an expired service password) shows its exact error in the server’s row or form, so it can be fixed before a real outage.

Benefits and metrics

  • Time to learn about an outage: seconds, through an alert, instead of reports from users.
  • Number of uncontrolled server shutdowns during a power outage: the target is zero.
  • For each group: the remaining runtime compared with the shutdown threshold, visible in real time.
  • For each server, the result of the last shutdown (successful or failed), visible on the group page.
  • The number of UPS units online, on battery, and offline, in the module header; on the main dashboard, how many UPS units are online out of the total and how many are on battery.

2Level 2

For the IT team

Integrations, requirements, roles, control, and known limitations.

Compatible equipment

  • UPS units with an SNMPv3 network management card (with authentication and encryption) or connected to a NUT server, including over USB or serial. Automatic discovery looks for UPS units in a subnet and marks the ones already added.
  • Servers that can be shut down: Linux, Proxmox, VMware ESXi, TrueNAS, and Synology (over SSH), Windows Server and Hyper-V (over WinRM), Proxmox hosts also through their API, and physical servers also through their management controller (IPMI or Redfish). Each type has a default shutdown command, which can be changed.
  • Startup: Wake-on-LAN, manually or automatically after power returns, with a configurable delay.
  • Optionally, each server can call its own web address (webhook) before shutdown and after power returns.
  • Outages reach SOC automatically, as infrastructure alerts, and UPS units and their servers appear on the infrastructure map in Monitoring.

What you configure

  • On each server: automatic shutdown, the runtime threshold at which it shuts down, and a delay, so that shutdowns are staggered. The shutdown order is shown on a timeline.
  • On each group: how runtime is calculated when the group has several UPS units. There is an option suited to servers with redundant power supplies, an average-based option, and a conservative one.
  • For the whole module: the recipients and levels of email and SMS alerts, in the module’s configuration on the server.

Guarantees during an outage

  • Shutdowns stay correct even if Monolit restarts during the outage, if a UPS reading fails, or if power returns only briefly: the outage is not lost, and no server is shut down twice.
  • When power returns, only the servers that Monolit shut down during that outage start.
  • An interrupted or unconfirmed shutdown triggers a critical alert, so that the operator checks the server.
  • Restoring the platform from a backup does not replay shutdowns or startups from an old outage.

Roles and audit

  • The summary (the tile on the main dashboard) is visible to every account. Viewing readings, acknowledging alerts, and manually reading a UPS are for the IT team.
  • Configuration (UPS units, groups, and servers), discovery, the connection test, shutdown, group shutdown, and Wake-on-LAN are for administrators and the IT manager only.
  • For other accounts, the module does not appear in the menu and cannot be opened.
  • Passwords, SSH keys, and tokens are entered once and stored encrypted on the server. The interface shows only whether they exist.
  • Every shutdown and every Wake-on-LAN startup is recorded in the log, with who or what triggered the operation, its duration, and the full result of the command. The connection test is not logged: its result is shown only in the interface. For manual actions, the author is the signed-in account. Who acknowledged an alert is recorded in the same way.

Requirements

  • Network cards in the UPS units with SNMPv3, or a NUT server.
  • On the servers: a service account with the right to shut down (SSH with a key, WinRM enabled, a Proxmox token, or BMC access).
  • For Wake-on-LAN: the MAC address and WoL enabled in the BIOS or BMC.

Limitations

  • The shutdown and power-return behavior described above is verified by automated tests, but has not yet gone through a real outage. A controlled test during scheduled electrical maintenance is recommended.
  • Screens refresh periodically, not instantly.
  • The module does not yet have a schedule of maintenance windows, and the module’s settings are not edited in the interface. The group settings window also has fields for alert thresholds and recipients, which are not used yet.
  • Battery health does not yet have a dedicated screen.
  • The labels in the power-flow diagram are always in English, even in the Romanian interface.